Carterton WWTP

About the project

Carterton WWTP

UPG Pipe Systems have proudly supplied the Carterton District Council with the pipework for their upgraded WWTP. This project included 355mm Stream PE100 mains pipework feeding out to irrigators and many pre-fabricated sections for chamber connections, pump offtakes and a 355mm manifold (as pictured).

Many sections were originally specified in Stainless Steel but with the wide range of options that UPG could provide with with pre-fabrication most of the sections were converted to PE100. PE100 is ideal for this environment being quick to install, 100% UV resistant, zero corrosion risk, lightweight and harder wearing than Stainless Steel !!

Project Partners

Developer: Carterton District Council
Consulting Engineers: New Zealand Environmental Technologies (NZET)

Completion Date
2014
Services
UV Treatment System
Sector
Civil and Infrastructure

Other Civil and Infrastructure projects

Other projects