Greymouth WTP

COMPLETION DATE

April 2015

SERVICES

SECTOR

Civil & Infrastructure

Greymouth Water Treatment Plant

The Grey District Council required an upgrade to the Greymouth Water Treatment Plant to include UV Disinfection, increased on-site Treated Water Storage and a pH controlled solution to improve the existing Lime Dosing system.

Process Flow provided a total design/build solution which was integrated into the existing plant infrastructure and provided UV and chlorine disinfection as well as improved pH control through a robust Lime Dosing System.  

Process Flow commissioned the project in April 2015 and the new modern water treatment plant provides water to Greymouth and the surrounding districts in accordance with the ‘Drinking Water Standard New Zealand’ (DWSNZ)

The Project Included:

  • New bore pump controls
  • UV Disinfection 
  • Lime Storage via a 70m3 silo
  • New powder handling system and slurry tank
  • New 250m3 Reservoir
  • New PLC and SCADA system

This fully operational water treatment plant required carefully coordinated commission and cut-over planning, and had to maintain supply to a population of 10,000 people.

Source: Process Flow

Project Partners

Asset Owner: Grey District Council
Installer: Process Flow

Systems Employed

Stream PE100 Pressure